What the Indigenous nations filed

Four Indigenous nations take part in the review of the Tenas mine. This page gathers the documents the four nations placed on the public record, says what each document says, and follows what came of each nation’s requests.

In brief

The mine site lies in Wet'suwet'en territory (the Yintah), on the lands of two houses: Cas Yex and Kwen Bea Yex. The public registry holds ten documents that come from the nations or state the nations’ requests. The central one is a 2022 letter from the Office of the Wet'suwet'en saying that the company wrote its chapter on Wet'suwet'en title and rights without engaging the members of those two houses. Three months later the review ran past its legal deadline and moved, with the Office's agreement, under a newer law. That law gives each nation a formal say at the end: a notice of consent or non-consent that goes to the Ministers.

4participating Indigenous nations named by the EAO
10documents from the nations in the registry
97comments from three of the nations on the 2022 Application
51of them turned into formal Information Requests to the company
26of them left for the EAO to weigh in its own assessment
20of them closed, all from Wet'suwet'en First Nation

Comment counts are ours, from the status column of the EAO's tracking table as it stood on April 10, 2024, the latest version published. The Office of the Wet'suwet'en made 51 comments (26 to the Office’s Information Requests, 25 to the EAO's assessment); Witset First Nation made 26 (25 to Witset’s Information Requests, 1 to the EAO's assessment); Wet'suwet'en First Nation made 20 (all closed). A comment that is not closed was carried forward, not dropped. See the review timeline. The house names are spelled here as the Office of the Wet'suwet'en spells them in its letters; other documents write Cas Yikh.

Who the nations are

The EAO's Amendment Order of November 3, 2023 names the participating Indigenous nations for the Tenas Project. Source: Amendment Order, Nov 3, 2023, p. 2.

Before December 2022 the review named one body only: the 2019 order directed the EAO to consult "the Wet'suwet'en Nation through the Office of the Wet'suwet'en Hereditary Chiefs". Source: Section 11 Order, Jun 2019, p. 9.

The letters and requests

These are in date order. We have read each of them in full.

Request to stop the clock

FromOffice of the Wet'suwet'en DatedSeptember 10, 2022 Length4 pages

The Office asks the EAO to suspend the legal time limit on its review until Telkwa Coal fills "critical information gaps" by working directly with the members of the two affected houses, Cas Yex and Kwen Bea Yex. It says the company's chapter on Wet'suwet'en title and rights "has been completed as a desktop exercise only", with "no engagement" of house members in writing it.

It names three gaps: cultural data, cumulative effects data, and socio-economic data, each specific to the two house territories. It states that title and rights are held by the houses, "have never been surrendered or extinguished", and that finishing the review without this information "would represent a total failure of the BC EAO".

Source: Office of the Wet'suwet'en letter, Sep 10, 2022, p. 1; Office of the Wet'suwet'en letter, Sep 10, 2022, p. 2; Office of the Wet'suwet'en letter, Sep 10, 2022, p. 3.

Agreement to move the review under the 2018 Act

FromOffice of the Wet'suwet'en DatedOctober 20, 2022 Length3 pages

The Office calls the review under the 2002 Act "seriously flawed" and agrees to Telkwa Coal's proposal to move it under the 2018 Act in place of a suspension. It asks for "a transparent and consensus-based approach" to the move, and says it "must be directly involved" in deciding how the review continues.

It adds a condition: until funds are provided for the work plans, the Office "will not be in a position to meaningfully engage".

Source: Office of the Wet'suwet'en letter, Oct 20, 2022, p. 1; Office of the Wet'suwet'en letter, Oct 20, 2022, p. 2.

Confirmation as a participating nation

FromWitset First Nation DatedOctober 2022 Length2 pages, an email with names blacked out

A one-line reply to the EAO: "I can confirm that Witset First Nation intends to proceed as a participating Indigenous Nation." The registry file name gives the year as 2023; the email replies to an EAO message of October 25, 2022, and the Amendment Order dates the confirmation October 26, 2022.

Source: Witset First Nation email, Oct 2022, p. 1; Amendment Order, Nov 3, 2023, p. 1.

Confirmation as a participating nation

FromOffice of the Wet'suwet'en DatedNovember 2, 2022 Length1 page

The Office confirms it will take part under the 2018 Act, and sets out who decides. The 13 house groups "are the governing bodies"; the Office supports the house groups with "operational and technical assistance". The letter says it "must be clearly understood that the Office of the Wet'suwet'en is not authorized to make decisions on behalf of our house groups".

Source: Office of the Wet'suwet'en letter, Nov 2, 2022, p. 1.

Information Requests for the two houses

FromIssued by the EAO for the Office of the Wet'suwet'en DatedDecember 2022 Length1 page

Three requests, each to be met "through direct engagement with Cas Yex and Kwen Bea Yex House Groups and in collaboration with" the Office. Telkwa Coal must collect cultural data, cumulative effects data and socio-cultural data specific to the two house territories, and agree with the houses on the method for assessing cumulative effects.

Source: Information Requests: Office of the Wet'suwet'en, Dec 2022, p. 1.

Information Requests for Witset

FromIssued by the EAO for Witset First Nation DatedDecember 14, 2022 Length1 page

Five requests. The first three match those for the houses, specific to Witset First Nation. The fourth asks Telkwa Coal to commit to sharing all project information with Witset, including the company’s proposed "avoidance, mitigation, and accommodation measures". The fifth asks for an assessment of the project's effects on Witset's cultural and socio-economic values.

Source: Information Requests: Witset First Nation, Dec 14, 2022, p. 1.

Confirmation as a participating nation

FromWet'suwet'en First Nation DatedJanuary 9, 2023 Length1 page

Chief Maureen Luggi confirms that Wet'suwet'en First Nation "identifies as a participating Indigenous nation" for the review under the 2018 Act. The letter raises no issues about the project.

Source: Wet'suwet'en First Nation letter, Jan 9, 2023, p. 1.

Notice that Skin Tyee was left out

FromSkin Tyee First Nation DatedFebruary 9, 2023 Length4 pages

Chief Rosemarie Skin writes that the EAO "has excluded us" from the review: Skin Tyee was not notified of the project, of the move to the 2018 Act, or of the January 16, 2023 deadline to give notice. She asks the EAO to extend that deadline.

The letter says Skin Tyee is a member of the Office of the Wet'suwet'en, but that the Office "does not represent Skin Tyee in this matter", and that Skin Tyee’s interests "are not necessarily represented by the Wet'suwet'en Hereditary Chiefs". Skin Tyee’s stated concern is salmon: "Critical salmon harvesting sites are located in close proximity to the Project area", and it is "very concerned" about selenium reaching the fish.

Source: Skin Tyee First Nation letter, Feb 9, 2023, p. 1; Skin Tyee First Nation letter, Feb 9, 2023, p. 2; Skin Tyee First Nation letter, Feb 9, 2023, p. 3.

The two technical reports

The Office of the Wet'suwet'en commissioned two independent reviews of the company's Application from the Skeena Fisheries Commission. Both were posted to the registry in September 2022. We have read the sections cited and not every page.

Water and the Tenas Coal Project

FromAllison Oliver, Ph.D., Skeena Fisheries Commission, for the Office of the Wet'suwet'en Dated2022 Length30 pages

A review of the company's water chapters, written "to support decision-making processes by the affected House Groups".

The report refers to a separate plain-language summary for the two houses. We did not find that summary in the registry.

Source: Water report for the Office of the Wet'suwet'en, 2022, p. 3; Water report for the Office of the Wet'suwet'en, 2022, p. 12; Water report for the Office of the Wet'suwet'en, 2022, p. 14; Water report for the Office of the Wet'suwet'en, 2022, p. 21; Water report for the Office of the Wet'suwet'en, 2022, p. 22; Water report for the Office of the Wet'suwet'en, 2022, p. 28.

Fish and Fish Habitat and the Tenas Coal Project

FromKyla Warren, Skeena Fisheries Commission, for the Office of the Wet'suwet'en DatedMay 2022 Length28 pages

A review of the company's fish chapters. It states that it "will not contain advice on whether the project should be supported"; that decision is left to Wet'suwet'en decision makers.

Source: Fish report for the Office of the Wet'suwet'en, May 2022, p. 3; Fish report for the Office of the Wet'suwet'en, May 2022, p. 22; Fish report for the Office of the Wet'suwet'en, May 2022, p. 23; Fish report for the Office of the Wet'suwet'en, May 2022, p. 24; Fish report for the Office of the Wet'suwet'en, May 2022, p. 25; Fish report for the Office of the Wet'suwet'en, May 2022, p. 26; Fish report for the Office of the Wet'suwet'en, May 2022, p. 27.

Our reading of the company's 2026 water response →The ponds and dams, year by year →

What came of it

  1. Sep 6, 2019Telkwa Coal pauses the review until April 30, 2020 at the request of "the Cas Yikh house membership", during talks between the Wet'suwet'en and the Province. Source: Telkwa Coal letter, Sep 6, 2019, p. 1.
  2. Jul 8, 2020Telkwa Coal answers the Office of the Wet'suwet'en on moose killed by trains. The Office had asked for the moose population to be monitored. The company replies that its assessment "is habitat focussed" and that the Province monitors moose. Source: Telkwa Coal memo on moose and rail, Jul 8, 2020, p. 1; Telkwa Coal memo on moose and rail, Jul 8, 2020, p. 2.
  3. May 2022The registry dates the two technical reports written for the Office of the Wet'suwet'en to May 2022. They were posted to the registry on September 2, 2022.
  4. Sep 10, 2022The Office asks the EAO to suspend the time limit. Source: Office of the Wet'suwet'en letter, Sep 10, 2022, p. 1.
  5. Oct 20, 2022The Office agrees to move the review under the 2018 Act instead. Source: Office of the Wet'suwet'en letter, Oct 20, 2022, p. 1.
  6. Dec 14 to 16, 2022The EAO issues the Information Requests for the houses and for Witset, and makes them conditions of the Transition Order. The Order requires the EAO to "seek to achieve consensus with participating Indigenous nations" on whether the company's answers are sufficient. Source: Transition Order, Dec 16, 2022, p. 2; Transition Order, Dec 16, 2022, p. 6.
  7. Mar 1, 2023Skin Tyee First Nation confirms interest, three weeks after the Skin Tyee letter. Source: Amendment Order, Nov 3, 2023, p. 2.
  8. Nov 3, 2023An Amendment Order names four participating Indigenous nations, Skin Tyee among the four, and provides that each of the four nations may conduct an assessment of the project's effects on that nation and that nation’s rights. Source: Amendment Order, Nov 3, 2023, p. 2.
  9. Nov 24, 2025Telkwa Mining files answers to the Office's comments. It refers to three studies by the Office (a Wet'suwet'en Wellbeing Study, a Rights Impact Assessment and a Cultural Use Study) and says it "will discuss appropriate incorporation" of their results. In the same filing the company writes that the Office "did not grant Telkwa Mining's consultants the opportunity to interview House Groups during 2024 or in the first quarter" of 2025. Source: Section 25 matters response, Nov 24, 2025, p. 75; Section 25 matters response, Nov 24, 2025, p. 112; Section 25 matters response, Nov 24, 2025, p. 475.
  10. Aug 17, 2026The EAO accepts the company's answers. Its letter says it "sought to achieve consensus with participating Indigenous nations" on their sufficiency. It does not say whether consensus was reached. Source: EAO letter, Aug 17, 2026, p. 1.
  11. AheadThe EAO "will seek consensus with participating Indigenous nations" on its draft report and conditions. Each nation "may also provide a notice of consent or non-consent", which goes to the Ministers with the file. Source: EAO letter, Aug 17, 2026, p. 2.

The full review timeline →What's happening now →

What the company wrote about the nations

These documents are about the nations and were written by or for the company. They are listed so that the two kinds are not confused.

What the record does not show

Sources

  1. Office of the Wet'suwet'en letter, Sep 10, 2022
  2. Office of the Wet'suwet'en letter, Oct 20, 2022
  3. Office of the Wet'suwet'en letter, Nov 2, 2022
  4. Witset First Nation email, Oct 2022
  5. Amendment Order, Nov 3, 2023
  6. Information Requests: Office of the Wet'suwet'en, Dec 2022
  7. Information Requests: Witset First Nation, Dec 14, 2022
  8. Wet'suwet'en First Nation letter, Jan 9, 2023
  9. Skin Tyee First Nation letter, Feb 9, 2023
  10. Water report for the Office of the Wet'suwet'en, 2022
  11. Fish report for the Office of the Wet'suwet'en, May 2022
  12. Telkwa Coal letter, Sep 6, 2019
  13. Telkwa Coal memo on moose and rail, Jul 8, 2020
  14. Transition Order, Dec 16, 2022
  15. Section 25 matters response, Nov 24, 2025
  16. EAO letter, Aug 17, 2026
  17. Application Chapter 11, Wet'suwet'en, Part 1 (137 pages)
  18. Application Chapter 11, Wet'suwet'en, Part 2 (39 pages)
  19. Cultural Use Study, Appendix 11.0-A (122 pages)
  20. Appendix 11.0-B, Delgamuukw Map 22, fishing sites
  21. Indigenous Consultation and Engagement Plan, Aug 30, 2021
  22. Indigenous Engagement and Consultation Report, Apr 2022
  23. Indigenous Consultation and Engagement Report 2, Aug 2022
  24. Section 11 Order, Jun 2019